Opinion and news · Rural paths · November 2026

The rural paths of our districts are as bad as ever

Sunken asphalt, potholes and puddles, trenches not reinstated and bank guarantees not called in. And €520,000 announced, with no word on where it is going.

Translated from the Catalan original. In case of discrepancy, the Catalan version prevails.

FOR YEARS we have been reporting the poor state of the rural paths in Lleida's districts. There is cracked and sunken asphalt, and dirt stretches full of potholes and puddles. Nothing has changed.

Asphalt path with the surface broken into plates and holes filled with gravel
AsphaltThe surface has broken up into plates, exposing the base layer. November 2026.

The photographs in this article show what we find. On the asphalt paths, the surface is cracked and full of holes, and at one point the subsidence is marked only with warning tape. On the dirt paths, potholes and puddles make driving a risk for vehicles and farm machinery.

Subsidence at the edge of an asphalt path, surrounded only by red and white tape tied to the guardrail Asphalt path with alligator cracking and an open pothole in the middle
AsphaltLeft: subsidence at the edge of the path, marked only with tape. Right: cracks across the whole surface and an open pothole. November 2026.

On the dirt paths, one-off interventions do not solve the problem. This summer they were milled without adding any new material. It only raised dust, and within a few days the paths were the same or worse.

Dirt path between fruit trees with a long puddle covering half its width Dirt path with a large puddle covering almost its full width
DirtPuddles covering half or the full width of the path, months after the summer milling. November 2026.

On top of this came the works on the solar plants' grid connection lines, carried out by both Solaria and Engie. The trenches have left subsidence and damage on the stretches of path where work was done, and the risk to traffic has kept growing.

Asphalt path with the power line trench covered by a strip of concrete broken into pieces
TrenchesThe trench, covered with a strip of concrete next to the asphalt, has already broken into pieces. November 2026.

The permits for these works require the paving to be reinstated «de manera immediata a la finalització dels treballs» [immediately on completion of the works] and require a bank guarantee. The guarantees add up to more than €727,000. The same permits allow trenches to be covered with concrete, but only temporarily and only when, for reasons beyond the company's control, reinstatement cannot be immediate: the final reinstatement must be in asphalt. Some of these works have already run past their execution deadline and, even so, the final asphalt has not been laid: where there was asphalt, there is now a concrete patch or a sunken surface. And where works are still within their deadline, the permit does not allow trenches to be left covered with temporary concrete indefinitely either: it requires the paving to be reinstated immediately and limits open trench to 100 metres.

Strip of temporary concrete along an asphalt path, full of cracks Trench concrete crumbled into plates and loose stones in the middle of the path
TrenchesThe concrete, which was meant to be temporary, is cracking and crumbling. The final asphalt has still not been laid. November 2026.

In June we submitted a formal demand to the Paeria (Lleida City Council) and to the Working Group of the Horta Commission. We asked for an inspection of all the affected paths, an immediate order to the companies, and the calling-in of the guarantees or works carried out by the Council at the companies' expense. We are not aware of the Paeria having called in any guarantee. According to the information available to us, the municipal technical staff did not review the situation until 6 November.

Concrete patch on a path, with a pile of rubble on the verge and a yellow construction fence Trench crossing an asphalt path, backfilled only with soil and gravel
TrenchesLeft: rubble and a construction fence abandoned on the verge. Right: a trench crossing the path, backfilled only with soil and gravel. November 2026.
«We have been warning for months, and the surface is still sunken.»
Dirt path under a power line, with tractor ruts and a row of puddles
DirtRuts and chains of puddles along the path. November 2026.

Meanwhile, the Paeria has announced €520,000 this year for the renovation, signage and clearing of the Horta's rural paths. The press reports one intervention, the final stretch of the Camí de Vallmanya between Torres de Sanui and Alpicat, the first of three phases. We do not know which other paths are included or how much each one costs. The paths in our districts are as bad as ever.

Dirt path seen from a car, with a row of potholes across it Dirt path seen from a car, with puddles beside the sown fields
DirtPotholes and puddles in spring. April 2026.

We ask that the companies leave the paths as they found them and that the Paeria enforce the conditions it imposed itself. We also ask it to publish the list of paths included in the €520,000, with the amount and schedule for each, so that residents can check where the money goes.

We will keep reporting this until the paths are passable again.

Associació de Veïns Horta Sud de Lleida