Solar plants and power lines
The Horta Sud and the neighbouring municipalities have a concentration of photovoltaic plant projects, their connection lines and two 220 kV transmission lines. The map shows the projects registered by the Generalitat within the area of our districts.
Source: Generalitat de Catalunya, layers of solar plant projects and their connection lines (polygons and routes; capacity in MW, area in ha, permitting status). The projects shown are those touching the map area, which includes part of Albatàrrec, Alfés, Els Alamús and other neighbouring municipalities. Limonium tournefortii area: the Generalitat's public layer of Areas of faunal and floral interest. District boundaries: the association's layer based on the Lleida City Council KML.
The projects, one by one
| Plant | File | MW | ha | Status | Environmental procedure |
|---|
PSFV La Vinatesa
A 6.205 MW plant on 13.04 ha of non-developable land, in the municipalities of Lleida and Albatàrrec. It is under review with file number FUE-2024-03787940.
In March 2026 the association submitted objections. It asks to be recognised as an interested party and to access the full file, and points out that this is not an isolated project: nearby there are Sol de Vinatesa, Sol de Perera, Miret, El Tossalet, Sol del Segre, La Femosa and Helmi Solar.
Building all these plants together would mean a significant transformation of the Horta de Lleida: extensive occupation of farmland, alteration of the landscape, more energy infrastructure and fragmentation of the fields.
The 220 kV lines
Mangraners–Juneda–l'Espluga–Begues
In May 2025 the Generalitat authorised an addendum to the project to convert this Red Eléctrica line to double circuit (Resolution TER/1781/2025). The Torreblanca PDU reserves land to divert its route.
Since 22 October 2026 the fourth addendum has been open to public consultation: a new 6 km route between towers T-7 and T-31, with 21 new towers through Quatre Pilans and the Terme de Grealó.
Mangraners–Peñalba
A 220 kV double-circuit overhead and underground line between the Mangraners substation and the Peñalba substation (Huesca), processed by the Spanish State. It runs through Vinatesa, la Femosa and Quatre Pilans.