The intermodal station
The Generalitat wants to build a freight rail terminal next to the Torreblanca–Quatre Pilans estate, alongside the Lleida–Barcelona line. Here we gather what has been published about it, with the date and source of each figure.
- Official name
- Plana de Lleida rail terminal
- Promoter
- Generalitat · Directorate-General for Mobility Infrastructure
- Land reserve
- 120 ha, outside the estate sector
- Capacity
- Up to 12,000 trains/year
- Cost
- €131m (feasibility study, 2025) · €72m allocated to the first phase (Catalan Government, 2026)
- Works
- Planned start in 2027 (forecast of March 2025)
What is to be built
The feasibility study draws a strip parallel to the main line, with a new access road from the north, a roundabout, the main building and car and lorry parks.
Planned facilities
- 5 dispatch and reception tracks.
- 4 container loading and unloading tracks.
- 1 loading and unloading track with silos for the agri-food sector.
- Space for a possible rolling motorway, that is, lorries carried on the train.
- Operating and maintenance tracks, locomotive sidings, main building and parking for heavy and light vehicles.
Why, according to the Generalitat
The Generalitat places the terminal on the Mediterranean Corridor and the future Transversal Rail Axis. According to its 2023 data, rail carries between 2.6 % and 4.3 % of goods transported overland in Catalonia, depending on whether internal transport is counted. The study's presentation credits the terminal with a saving of 500,000 tonnes of CO₂ equivalent a year.
These are the Generalitat's figures; the association has not been able to verify them.
Where it stands
- The initial approval of the Torreblanca PDU includes an Intermodal Centre sector of 82.7 ha on non-developable land, to be implemented through expropriation.
- CIMALSA signs an agreement with the European Investment Bank to study Catalonia's terminal plan.
- Technical approval of the feasibility study and the environmental impact study.
- Public consultation on the feasibility study and the environmental impact study, published in the DOGC. The Generalitat expected the environmental impact statement in summer 2025, final approval in December 2025 and the start of works in 2027.
- The PDU receives final approval. The intermodal sector disappears and its place is taken by a temporary land reserve for the terminal.
- The Catalan Government approves the Catalan rail terminal strategy: €127m up to 2031 for four terminals. Lleida's receives €72m for construction and is the most advanced.
In 2025 the Generalitat put the cost of building the terminal at €131m. The €72m announced in 2026 correspond to the first phase of the strategy. None of the sources consulted explains the difference between the two figures.
A reserve that conditions the estate
The PDU approved in 2026 does not plan the terminal: it reserves land for it «fins al moment en què s'hagi aprovat l'estudi informatiu preceptiu» [until the mandatory feasibility study has been approved]. While the reserve lasts, the land does not change classification, but it is subject to the use restrictions of railway protection.
Once the feasibility study is approved, the implementation system and the expropriations will be decided by the railway authority, not by the PDU.
The terminal also conditions the pace of the estate. In phase 2, the 134.9 ha giga-plot, no activity may begin until the terminal study is approved.




Sources: Generalitat de Catalunya, presentation «Impulsem l'estació intermodal de Lleida» and presentation of the feasibility study for the Plana de Lleida rail terminal (March 2025); Catalan Government press release, 19/03/2025; VIA Empresa, 15/09/2026; ON Economia, 15/09/2026; PDU for economic activity in the Plana de Lleida (initial approval 2022 and final approval 2026).
More information: project page at the Department of Territory · Segre, 15/09/2026.