Infrastructure

The intermodal station

The Generalitat wants to build a freight rail terminal next to the Torreblanca–Quatre Pilans estate, alongside the Lleida–Barcelona line. Here we gather what has been published about it, with the date and source of each figure.

Official name
Plana de Lleida rail terminal
Promoter
Generalitat · Directorate-General for Mobility Infrastructure
Land reserve
120 ha, outside the estate sector
Capacity
Up to 12,000 trains/year
Cost
€131m (feasibility study, 2025) · €72m allocated to the first phase (Catalan Government, 2026)
Works
Planned start in 2027 (forecast of March 2025)
The project

What is to be built

The feasibility study draws a strip parallel to the main line, with a new access road from the north, a roundabout, the main building and car and lorry parks.

Layout of the terminal on an orthophoto: dispatch and reception tracks, loading area, bulk silos, main building, roundabout and access road, parallel to the main line
Layout of the terminal on an orthophoto. Source: Generalitat de Catalunya, presentation of the feasibility study for the Plana de Lleida rail terminal (March 2025).

Planned facilities

  • 5 dispatch and reception tracks.
  • 4 container loading and unloading tracks.
  • 1 loading and unloading track with silos for the agri-food sector.
  • Space for a possible rolling motorway, that is, lorries carried on the train.
  • Operating and maintenance tracks, locomotive sidings, main building and parking for heavy and light vehicles.

Why, according to the Generalitat

The Generalitat places the terminal on the Mediterranean Corridor and the future Transversal Rail Axis. According to its 2023 data, rail carries between 2.6 % and 4.3 % of goods transported overland in Catalonia, depending on whether internal transport is counted. The study's presentation credits the terminal with a saving of 500,000 tonnes of CO₂ equivalent a year.

These are the Generalitat's figures; the association has not been able to verify them.

Permitting

Where it stands

  1. The initial approval of the Torreblanca PDU includes an Intermodal Centre sector of 82.7 ha on non-developable land, to be implemented through expropriation.
  2. CIMALSA signs an agreement with the European Investment Bank to study Catalonia's terminal plan.
  3. Technical approval of the feasibility study and the environmental impact study.
  4. Public consultation on the feasibility study and the environmental impact study, published in the DOGC. The Generalitat expected the environmental impact statement in summer 2025, final approval in December 2025 and the start of works in 2027.
  5. The PDU receives final approval. The intermodal sector disappears and its place is taken by a temporary land reserve for the terminal.
  6. The Catalan Government approves the Catalan rail terminal strategy: €127m up to 2031 for four terminals. Lleida's receives €72m for construction and is the most advanced.

In 2025 the Generalitat put the cost of building the terminal at €131m. The €72m announced in 2026 correspond to the first phase of the strategy. None of the sources consulted explains the difference between the two figures.

Relationship with the estate

A reserve that conditions the estate

The PDU approved in 2026 does not plan the terminal: it reserves land for it «fins al moment en què s'hagi aprovat l'estudi informatiu preceptiu» [until the mandatory feasibility study has been approved]. While the reserve lasts, the land does not change classification, but it is subject to the use restrictions of railway protection.

Once the feasibility study is approved, the implementation system and the expropriations will be decided by the railway authority, not by the PDU.

The terminal also conditions the pace of the estate. In phase 2, the 134.9 ha giga-plot, no activity may begin until the terminal study is approved.

The Torreblanca–Quatre Pilans industrial estate

Official plan documents · 2022 and 2026
2022 regulations, article 45.4: the PDU defines and plans the Torreblanca-Quatre Pilans Intermodal Centre Sector, sector area 826,775 square metres
2022 regulations, article 90: given the public-utility nature of this area, the action will be implemented through expropriation
2026 regulations, article 43: the land reserve for the multimodal terminal is intended to be temporary until the mandatory feasibility study has been approved
2026 regulations, article 62.9: in the giga-plot zone no economic activities may begin until the feasibility study for the intermodal terminal has been approved
Urban planning regulations of the PDU. Initial approval (2022): article 45.4, Intermodal Centre sector, and article 90, management conditions. Final approval (2026): article 43, reserve land for the terminal, and article 62.9, giga-plot. Highlighting by the association.

Sources: Generalitat de Catalunya, presentation «Impulsem l'estació intermodal de Lleida» and presentation of the feasibility study for the Plana de Lleida rail terminal (March 2025); Catalan Government press release, 19/03/2025; VIA Empresa, 15/09/2026; ON Economia, 15/09/2026; PDU for economic activity in the Plana de Lleida (initial approval 2022 and final approval 2026).

More information: project page at the Department of Territory · Segre, 15/09/2026.