We are challenging the Torreblanca plan before the High Court of Justice of Catalonia
The Associació de Veïns de l'Horta Sud de Lleida has filed a judicial review appeal (recurs contenciós administratiu) against the final approval of the master plan for the Torreblanca–Quatre Pilans industrial estate. The approved plan is not the one that was put out to public consultation.
Translated from the Catalan original. In case of discrepancy, the Catalan version prevails.
The appeal challenges the decision of the Catalan Territorial Commission of 24 March 2026, which gave final approval to the Urban Master Plan for Economic Activity in the Plana de Lleida. The decision was published in the DOGC on 4 September.
Why we are appealing
- The approved plan is not the one put out to the public. The three sectors are reduced to one. The implementation system changes from expropriation to cooperation, and the intermodal sector and the link with the N-240 disappear. None of these changes was put out to public consultation again.
- The loss of farmland. The plan's study of agricultural impacts acknowledges that the loss of farmland cannot be offset, and it does not justify why there are no alternatives outside the Horta.
- The water report. The report from the Ebro Hydrographic Confederation is presented as unconditionally favourable, but the report sets conditions and warns of possible shortcomings.
- Risky industries. The regulations allow Seveso activities, with a risk of major accidents, without assessing their impact, and leave the assessment until each company sets up there.
We explain it in detail, with screenshots of the official documents, in Four years to make it worse and in We want an agri-food estate, not a risk estate.
And then there are the numbers. The plan expects to sell the land at €120/m², while in Aragon there is public industrial land at between €25 and €69/m². At that price, the margin on the operation is only €5.23 per square metre. We explain it in Torreblanca: the numbers depend on land at €120/m² and a terminal that still has no date.
What the press has said
- Segre, 4 November 2026 (in Catalan)
- La Manyana, 5 November 2026: «Veïns de l'Horta recorren el pla director del futur polígon de Torreblanca» (in Catalan)
We are asking for common sense
Lleida needs land for economic activity, but not at any price or in any way.
We are asking for someone to bring common sense to this estate: an estate designed to provide jobs for the people of Lleida, with agri-food rather than chemical industry right next to the city, and with costs that do not make it unviable before it even starts.
Associació de Veïns de l'Horta Sud de Lleida
The Torreblanca–Quatre Pilans industrial estate
The Torreblanca numbers: land at €120/m² and the terminal with no date
Four years to make it worse: the 2022 plan and the 2026 plan
All articles
Sources: Decision of the Catalan Territorial Commission of 24/03/2026 giving final approval to the PDU for economic activity in the Plana de Lleida, published in DOGC no. 9745, of 4/09/2026; Segre, 4/11/2026; La Manyana, 5/11/2026.